Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.

Unlimited Access

Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.

Exam PMP topic 1 question 1135 discussion

Actual exam question from PMI's PMP
Question #: 1135
Topic #: 1
[All PMP Questions]

A project manager is in the middle or handling a major upgrade to an existing product. The project manager learns that the resources initially promised as part or the project are being moved to another priority project.

What should the project manager do?

  • A. Perform an impact analysis to see the effect on the project
  • B. Examine ways of modifying the scope of the project.
  • C. Adopt a resource leveling procedure to level the resources
  • D. Retrieve the documentation that shows the resource allocation
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
PeterCK
2 weeks, 4 days ago
Selected Answer: A
simple question
upvoted 1 times
...
Victory007
3 months, 2 weeks ago
Selected Answer: A
This will help the project manager understand how the change in resources will affect the project’s timeline, cost, and quality. Based on the results of the impact analysis, the project manager can then make informed decisions about how to proceed, such as negotiating for additional resources, adjusting the project schedule, or modifying the project scope.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...