What is a standardized, effective, and efficient way to manage changes to project documentation?

  • A. A change control board
  • B. A requirements traceability matrix
  • C. A configuration management system
  • D. A configuration verification and audit system
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
xRae
12 months ago
Selected Answer: C
BA Practice Guide 5.8.2.1 Configuration Management System (CMS) Configuration management helps to ensure the product or service being built conforms to its approved requirements. It provides a process to verify this conformance, document changes, and report the status of each change throughout the project life cycle. It includes documentation, a tracking process and defined approval levels necessary for authorizing changes. Configuration management for business analysis ensures that (a) the requirements and requirements-related documents are stored where they can be easily accessed by project stakeholders and are safeguarded from loss; and (b) access to previous versions of documents is available when needed.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...