Exam PgMP topic 1 question 319 discussion

Actual exam question from PMI's PgMP
Question #: 319
Topic #: 1
[All PgMP Questions]

A program is near completion and the benefits will be delivered shortly. The program manager prepares to initiate program closeout activities to release the program resources.
Before initiating closeout and releasing the resources, what should the program manager do?

  • A. Review the benefits management plan with the program sponsor
  • B. Obtain approval from the sponsor to close the program
  • C. Prepare performance evaluations for all program personnel
  • D. Prepare performance evaluations for all project personnel
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
hanyulin
11 months, 3 weeks ago
Selected Answer: A
A is the right answer
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...