A new quality report was distributed to stakeholders after the sponsor approved it. A senior manager requests changing the colors and sizes of some of the graphs included in the report.
What should the project manager do?
A.
Reject the change as the report was approved previously.
B.
Incorporate the change in a future report.
C.
Ask the team to make the manager's requested changes.
Advise the manager to raise a change request.
This ensures that the requested changes go through the formal change control process, maintaining the integrity of the project's documentation and ensuring appropriate review and approval of any modifications.
Because it needs to be discussed widely especially with the affected stakeholders. A change request initiates these conversations
upvoted 1 times
...
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
6 months, 2 weeks ago517f9da
1 year agoUppersquareCapital
1 year, 2 months agoDD_PMP
1 year, 2 months ago[Removed]
1 year, 3 months ago2121421
1 year, 3 months agoTrytrio
1 year, 4 months agoNathan4real21
1 year, 4 months ago