exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 396 discussion

Actual exam question from PMI's CAPM
Question #: 396
Topic #: 1
[All CAPM Questions]

During a kickoff meeting, the project sponsor presents a very ambitious project. Unfortunately, the stakeholders are not very excited as the work associated with the new project seems inefficient.

What could be missing from the business case?

  • A. Approval from the stakeholders
  • B. Root cause analysis of the problem
  • C. Work breakdown structure (WBS)
  • D. Feasibility study of the solution
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
8a6d137
1 week, 2 days ago
Selected Answer: B
Answer B is Correct. Business Case itself is considered a Economic feasibility study document. they are asking what is "missing'. Root cause is the correct answer meaning how they are going to fix bigger problem by initiating the project.
upvoted 1 times
...
flee
10 months, 1 week ago
Selected Answer: D
D definitely
upvoted 1 times
...
Mizbee
1 year, 2 months ago
Selected Answer: D
The correct answer is D: Feasibility study of the solution
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago