Question #: 338
Topic #: 1
[All CAPM Questions]

An organization is faced with increasing demand from the board of directors. They say budgets are flexible as long as the work gets completed.

What project management approach should the organization use?

  • A. Predictive
  • B. Iterative
  • C. Adaptive
  • D. Hybrid
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month, 1 week ago
Selected Answer: C
Why the other options are less appropriate: A. ❌ Works best when scope, time, and cost are well defined and fixed—not ideal for changing priorities. B. ❌ Allows for refinement but doesn’t fully embrace continuous change or flexibility in scope like adaptive does. D. ❌ Combines predictive and adaptive methods—could work, but the scenario specifically favors flexibility, which is core to adaptive alone.
upvoted 1 times
...
ebbff63
8 months, 1 week ago
Selected Answer: C
C- Adaptive It provides the flexibility and responsiveness to changing requirements and priorities.
upvoted 1 times
...
shubu2276
11 months, 4 weeks ago
Selected Answer: C
C. Adaptive approach
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...