Exam PgMP topic 1 question 46 discussion

Actual exam question from PMI's PgMP
Question #: 46
Topic #: 1
[All PgMP Questions]

Your program has a budget at completion of $1,550,000 and is expected to last one year.
Currently your program is 45 percent complete and has spent $725,000. According to the program schedule you are actually to be fifty percent complete by this time, but due to some vendor delays your program is running just a bit late. Based on this information which is performing worse, the cost or schedule?

  • A. The schedule is performing worse because the SPI is .90
  • B. The cost is performing worse because the EAC is $1,611,111.
  • C. The schedule is performing worse because the SV is -$27,500.
  • D. The cost is performing worse because the CPI is .96.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Nugi
4 months, 2 weeks ago
Selected Answer: A
Explanation: • BAC = 1,550,000 • AC = 725,000 • EV = (BAC * 0.45) = (1,550,000 * 0.45) = 697,500 • PV = planned % * BAC = 0.50 * 1,550,000 = 775,000 • CPI = EV / AC = 697,500 / 725,000 = 0.96 • SPI = EV / PV = 697,500 / 775,000 = 0.90
upvoted 1 times
...
happykaur
8 months, 3 weeks ago
Selected Answer: A
The answer is obvious from the options. SPI of 0.9 is worse than CPI of 0.96
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago