Why the other options are incorrect:
B. Daily standup
➤ This is a daily meeting during the iteration, not one that occurs after the iteration ends.
C. Backlog refinement review
➤ There is no formal "backlog refinement review." Backlog refinement is an ongoing activity, not a post-iteration meeting.
D. Iteration planning
➤ This happens before the next iteration starts, not after the previous one ends. It's used to plan what will be done next, not to reflect on the past.
A. Retrospective
A retrospective is a crucial meeting held at the end of each iteration in an adaptive project management environment to reflect on the completed iteration, identify what worked well, what didn't, and what can be improved for future iterations.
this one of the questions in today's exam [ 03/12/2024
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
JesseChou_123
1 month agoVangelis_1980
1 year agolamiaa
1 year, 4 months ago