Why the other options are incorrect:
A. Project manager
➤ The project manager may contribute, but does not own the business case. Their role begins after the project is authorized.
B. Project stakeholders
➤ Stakeholders may provide input or review it, but they are not responsible for developing it.
C. Project team
➤ The project team typically doesn't exist yet when the business case is being created.
D. Project sponsor
The project sponsor is typically responsible for the business case development document.
They have the authority and organizational backing to champion the project and secure necessary resources.
this one of the questions in today's exam [ 03/12/2024
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.