SPI = Earned Value (EV) / Planned Value (PV)
Given:
EV = 30
PV = 15
Therefore,
SPI = 30 / 15 = 2
So the answer is D: 2.0
Important note: An SPI greater than 1 indicates that the project is ahead of schedule.
this one of the questions in today's exam [ 03/12/2024
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Vangelis_1980
9 months, 1 week agolamiaa
1 year, 1 month ago