An intern is replacing a critical resource midway through a sprint. To help the intern get up to speed, the project manager assigns a senior engineer in the team as the intern's mentor. Two months later, the project goes into critical status, delaying the release milestone by a month.
What should the project manager have done to avoid this scenario?
Aditech
Highly Voted 1 year, 1 month agoNimitto
Most Recent 6 months, 2 weeks agovictory108
7 months agoc8ee0e6
11 months ago