An agile team has been assigned to a project that mandates the implementation of changes to key government products. The team has been given 6 months to fulfill this mandate.
What should the team lead do next?
A.
Create the project charter and statement of work (SOW) to estimate the changes and the scope of the change.
B.
Create all of the stories just for the next sprint and skip the epics until the next sprint.
C.
Create all of the stories needed to fulfill this change, document them in the backlog, and prioritize them according to business value.
D.
Create the epics at a high level for the requirements and begin grooming sessions.
C. Create all of the stories needed to fulfill this change, document them in the backlog, and prioritize them according to business value.
Because prioritization of product requirement to meet the mandate in 6 months
D
An agile team has been assigned to a project that mandates the implementation of changes to key government products. The team has been given 6 months to fulfill this mandate.
What should the team lead do next?
Adigun
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
52d1fe0
5 days, 2 hours agoAditech
3 weeks ago