Exam PgMP topic 1 question 18 discussion

Actual exam question from PMI's PgMP
Question #: 18
Topic #: 1
[All PgMP Questions]

Mike is the program manager of the NHQ Program. Mike and a vendor are in disagreement over the deliverable the vendor has created for Mike's program. Mike does not believe the vendor has correctly created the deliverable, while the vendor is adamant that his company has indeed completed the contract. Both parties have documented their stance in the debate.
This is an example of what?

  • A. Breach of contract
  • B. Issue
  • C. Risk
  • D. Claim
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
FareedKamran
2 weeks, 2 days ago
Selected Answer: B
its an issue and need to be logged in issue log.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.