During the fourth sprint, a project manager noticed that none of the customer representatives have participated in any of the sprints. The team told the project manager that they had a prototype ready.
What should the project manager do next?
A.
Contact the customer to confirm that they received updates of the work in progress (WIP).
B.
Tell the team to create a prototype manual to provide guidance for the end user.
C.
Deliver a presentation about the capabilities to the quality assurance (QA) team.
D.
Invite the customer representatives to the review meeting to review the prototype with the team.
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
info.samadov
6 months, 2 weeks agoLuffy113
6 months, 3 weeks agonicknamesdx
6 months, 3 weeks ago