A risk was identified at the beginning of a project, and a response plan was established. Unforeseen consequences resulted in a higher level of risk. The project manager has an idea that could address the new risk in an efficient way, but the response is different from the original risk mitigation plan.
What should the project manager do?
victory108
7 months agoSunshine2022
11 months, 3 weeks agoompk
11 months, 3 weeks agoompk
11 months, 3 weeks ago