Exam PMP topic 1 question 965 discussion

Actual exam question from PMI's PMP
Question #: 965
Topic #: 1
[All PMP Questions]

During a planning session, the development team and the product owner are arguing about the effort needed to deliver a specific feature in a software development project. The product owner says that the feature can be developed in one week, whereas the team estimates that it will take at least two weeks. After several hours of discussion, they have not reached an agreement.

What should the project lead do?

  • A. Decide what should be the time estimate and proceed with the planning meeting.
  • B. Educate the product owner that the project team members are the most appropriate group for assessing the effort.
  • C. Ask the project team to accept the shorter estimate as it is important to keep a good relationship with the product owner.
  • D. Communicate to the stakeholders that the project has to be delayed for two weeks.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
6 months, 2 weeks ago
Selected Answer: B
B. Educate the product owner that the project team members are the most appropriate group for assessing the effort
upvoted 1 times
...
517f9da
1 year ago
Selected Answer: B
B. Educate the product owner that the project team members are the most appropriate group for assessing the effort. The project team has the expertise and technical knowledge to accurately estimate the effort required to deliver the feature. This approach fosters mutual respect and trust, ensuring that realistic timelines are established based on the team's assessment.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...