A project manager regularly sends out project progress reports. However, there have been a few complaints from stakeholders who expressed that the communication does not meet their needs.
What should the project manager do?
A.
Communicate the project details to the stakeholders.
B.
Introduce a separate stakeholder engagement meeting.
C.
Analyze the communication needs of the stakeholders.
D.
Communicate progress more frequently to the stakeholders.
C. Analyze the communication needs of the stakeholders.
Understanding and addressing the specific communication needs of stakeholders ensures that the information shared is relevant and useful to them.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
6 months, 2 weeks ago517f9da
1 year ago