Actual exam question from PMI's PMP
Question #: 971
Topic #: 1
[All PMP Questions]

A project manager regularly sends out project progress reports. However, there have been a few complaints from stakeholders who expressed that the communication does not meet their needs.

What should the project manager do?

  • A. Communicate the project details to the stakeholders.
  • B. Introduce a separate stakeholder engagement meeting.
  • C. Analyze the communication needs of the stakeholders.
  • D. Communicate progress more frequently to the stakeholders.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
6 months, 2 weeks ago
Selected Answer: C
C. Analyze the communication needs of the stakeholders
upvoted 1 times
...
517f9da
1 year ago
Selected Answer: C
C. Analyze the communication needs of the stakeholders. Understanding and addressing the specific communication needs of stakeholders ensures that the information shared is relevant and useful to them.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...