Exam PMP topic 1 question 986 discussion

Actual exam question from PMI's PMP
Question #: 986
Topic #: 1
[All PMP Questions]

A project manager has been approached by the project sponsor about adding to the project scope. How should the project manager accommodate this request?

  • A. Disregard the request since the project scope is finalized
  • B. Adjust the project schedule to accommodate the new project scope requests.
  • C. Create a change request for the change control board (CCB) to review.
  • D. Update the project team about the change request.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
6 months, 2 weeks ago
Selected Answer: C
C. Create a change request for the change control board (CCB) to review
upvoted 1 times
...
517f9da
1 year ago
Selected Answer: C
C. Create a change request for the change control board (CCB) to review. Explanation: Creating a change request and submitting it to the change control board ensures that any modifications to the project scope are formally evaluated, approved, and documented. This process helps maintain project control and alignment with stakeholder expectations.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.