A project manager is managing the opening of a new office overseas. At the beginning of the project, possible delays due to legal permits are raised by one stakeholder. Subject matter experts (SMEs) reassessed the concern and suggested assigning more time for this permit, and the change control board (CCB) agrees.
Which document should the project manager update first to document this change?
kkkyyyy
2 months, 1 week agosblivia
4 months, 3 weeks ago8a6d137
2 weeks, 6 days ago7579ad3
7 months, 1 week agoNimitto
8 months, 3 weeks agovictory108
10 months, 3 weeks agoAnhHN11
11 months, 2 weeks agoBStub30
1 year agoc8ee0e6
1 year, 1 month agokevzzz
1 year, 2 months agoompk
1 year, 2 months agoUppersquareCapital
1 year, 3 months ago