A project manager is managing the opening of a new office overseas. At the beginning of the project, possible delays due to legal permits are raised by one stakeholder. Subject matter experts (SMEs) reassessed the concern and suggested assigning more time for this permit, and the change control board (CCB) agrees.
Which document should the project manager update first to document this change?
sblivia
1 month, 2 weeks ago7579ad3
3 months, 4 weeks agoNimitto
5 months, 2 weeks agovictory108
7 months, 2 weeks agoAnhHN11
8 months, 1 week agoBStub30
8 months, 4 weeks agoc8ee0e6
10 months agokevzzz
11 months, 1 week agoompk
11 months, 3 weeks agoUppersquareCapital
11 months, 4 weeks ago