exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1283 discussion

Actual exam question from PMI's PMP
Question #: 1283
Topic #: 1
[All PMP Questions]

While managing a project using a hybrid approach, the project manager realizes that there is a high level of rework due to quality issues. Because of that, each feature is taking longer than initially estimated.

What should the project manager do to address the issue?

  • A. Address the issue during the next sprint planning meeting.
  • B. Extend the dates for future project milestones.
  • C. Initiate a change request to extend the project end date.
  • D. Escalate the issue to the project sponsor.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
sblivia
1 month ago
Selected Answer: A
By discussing the quality issues and the resulting rework during the sprint planning meeting, the project manager can collaborate with the team to identify the root causes and implement corrective actions. This proactive approach allows the team to adjust their processes, improve quality, and reduce rework, ultimately helping to keep the project on track and meet the estimated timelines for each feature.
upvoted 1 times
...
victory108
7 months, 1 week ago
Selected Answer: A
A. Address the issue during the next sprint planning meeting
upvoted 1 times
...
UppersquareCapital
11 months, 3 weeks ago
Selected Answer: A
A. Address the issue during the next sprint planning meeting. This approach aligns well with agile practices. During the sprint planning meeting, the team can discuss the quality issues, identify the root causes, and agree on strategies to improve quality and reduce rework. This may include implementing stricter quality control measures, enhancing testing protocols, or providing additional training. Addressing the issue within the agile framework can help the team quickly adapt and improve their processes.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago