The company is a risk seeking organization, and has experienced measurable success based on their current strategy for growth. A new project has that exceeds the risk levels documented in the risk management plan.
What would be the best course of action for the company to take with the project based on its current scope?

  • A. Monitor ongoing risks closely for any major changes.
  • B. Perform a Monte Carlo simulation to understand possible risk outcomes.
  • C. Cancel the project, as the overall level of risk remains unacceptable.
  • D. Conduct a stakeholder meeting to validate stakeholder risk appetite.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MikeMarlo
6 months, 3 weeks ago
Selected Answer: B
Cancel the project without examining and having results is unacceptable at first. First thing to do is analyze consequences. So option B, quantify the risks you are having to check overall project risks in order to have some data to be able to decide. Then, be transparent and conduct stakeholder meeting (Option D) should be the next thing to do. Lastly, you could either cancel the project or Monitor closely (options C and A).
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.