exam questions

Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

Exam PMI-RMP topic 1 question 168 discussion

Actual exam question from PMI's PMI-RMP
Question #: 168
Topic #: 1
[All PMI-RMP Questions]

A new risk manager has been hired on a project and meets with the project director. The project director supplies the project’s risk register and asks the risk manager for an analysis of its effectiveness.

What two actions should the risk manager do next? (Choose two.)

  • A. Check for risk classification and that probability and impact are identified.
  • B. Check to ensure that the risk is supported by a Monte Carlo simulation.
  • C. Check to ensure the risk meeting agenda and supporting documents are distributed.
  • D. Check to ensure that risk origin, triggering event, and ownership is identified.
  • E. Check to ensure that the risks are gathered using Delphi technique.
Show Suggested Answer Hide Answer
Suggested Answer: CD 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MikeMarlo
6 months, 2 weeks ago
Selected Answer: AD
If we download a Risk Register from PMI webpage, we can see options A and D are in the file. So in order to see if the Risk Register has been updated in an effective way we should see parameters inside of this document. Checking meeting agendas is important for communication purposes but it is not related to the effectiveness of the documentation of the Risk Register
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...