A team is testing a product on multiple radio frequencies. The project manager is informed that a new government policy, expected in 2 weeks, will mandate companies to obtain approval and licensing for frequency testing. The team has completed 80% of the testing and needs 4 weeks to complete the remaining tests.
Which two actions should the project manager take until the approval is received? (Choose two.)
victory108
6 months, 3 weeks agotonybuivannghia
8 months, 3 weeks agoSaurav6233
11 months, 1 week agoSaurav6233
11 months, 1 week agotakaimomoGcup
11 months, 1 week agoUppersquareCapital
11 months, 2 weeks ago