Exam PMI-RMP topic 1 question 194 discussion

Actual exam question from PMI's PMI-RMP
Question #: 194
Topic #: 1
[All PMI-RMP Questions]

The project manager for project X was expecting the mobilization of critical equipment from another project, project Y. However, a day before the mobilization was scheduled, another project manager notifies project X’s project manager that the equipment would not be available for at least another month due to delayed activities for project Y. This has jeopardized meeting a critical milestone for project X.

How should project X’s project manager avoid this situation in the future?

  • A. Ask the other project manager to officially confirm the new date in writing
  • B. Request that the other project manager inform if any additional delays are expected
  • C. Request that the other project manager be added to relevant reports
  • D. Prepare a contingency response plan to implement when delays occur
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MikeMarlo
6 months, 2 weeks ago
Selected Answer: D
B is a reactive approach. D is a proactive approach where risk management is applied
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...