exam questions

Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

Exam PMI-RMP topic 1 question 220 discussion

Actual exam question from PMI's PMI-RMP
Question #: 220
Topic #: 1
[All PMI-RMP Questions]

A risk manager is confident that they have identified and quantified the risks and opportunities for a project. When presenting their work to management, on what areas should the risk manager focus? (Choose two.)

  • A. Risks as they apply to the organization’s overall risk management philosophy and strategic ambition.
  • B. Huge opportunities that possibly bring an additional 30% return for 10 projects in the next year.
  • C. Risks that are tied to the success of the organization.
  • D. Risk mitigation actions that will require work from stakeholders.
  • E. Risks related to cost that will impact the major projects that are currently in the execution phase.
Show Suggested Answer Hide Answer
Suggested Answer: CD 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MikeMarlo
6 months, 1 week ago
Selected Answer: AC
While options B, D, and E may also be important , they are not as directly tied to the organization's overall strategy. Therefore, they should be secondary considerations in the presentation to management.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...