Actual exam question from PMI's PMI-RMP
Question #: 226
Topic #: 1
[All PMI-RMP Questions]

During a risk reassessment workshop with the project team and some external stakeholders, two key external stakeholders are overemphasizing the impact of a few project risks. This has led to a conflict.

How should the risk manager handle this situation?

  • A. Request for a skilled facilitator to help resolve conflicts that have arisen.
  • B. Use the assumption analysis techniques to validate the assumptions.
  • C. Refer to the team’s ground rules on how to resolve conflicts.
  • D. Run a sensitivity analysis to check which risks have the most impact.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MikeMarlo
6 months, 2 weeks ago
Selected Answer: D
It is either B or D and I prefer D because we can check the quantitative assessment of the risks and which one have the most significant impact on the project. This way we can provide an objective clarification over the discussion. Remember that we are the Risk Manager, not the PM. If so, we could refer to the ground rules.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...