exam questions

Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

Exam PMI-RMP topic 1 question 244 discussion

Actual exam question from PMI's PMI-RMP
Question #: 244
Topic #: 1
[All PMI-RMP Questions]

During a project review meeting, stakeholders are making decisions on how to respond to known and new risks encountered during project execution. Which three artifacts should the stakeholders review? (Choose three.)

  • A. Risk register
  • B. Change log
  • C. Risk-adjusted back log
  • D. Assumption log
  • E. Basis of estimates
Show Suggested Answer Hide Answer
Suggested Answer: ACD 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MikeMarlo
6 months, 2 weeks ago
Selected Answer: ACD
Sorry! Risk Register Risk Adjusted Log >> Agile Backlog with included risks >> another way to have risks in the planning. Ensuring risks are considered, we can make decisions on how to respond to risks. Assumptions log Question 284 >> Risk Adjusted Backlog. I got confused because answer is/was Change Log and although Change Log is important to track changes, it is not so important to make decisions about Planning Risk Responses
upvoted 1 times
...
MikeMarlo
6 months, 2 weeks ago
Selected Answer: ABD
Risk Register >> Where all the risks are Change Log >> Tracking Changes Assumption Log >> Validating assumption and identifying new risks
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...