During the execution of a project to develop a prototype, the customer asks the project manager to stop the prototype line and purge a specific component based on recent reliability tests that have deemed the component to be deficient. The project manager checked the quality management plan and there is no reference to this component.
What should the project manager do next?
sblivia
3 months agovictory108
9 months agovictory108
6 months, 4 weeks agoNA1234567
10 months, 1 week agoKim222
10 months, 3 weeks agoKim222
10 months, 1 week agoAnitak
1 year agoUppersquareCapital
1 year, 1 month agoompk
1 year, 1 month ago