exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 337 discussion

Actual exam question from PMI's CAPM
Question #: 337
Topic #: 1
[All CAPM Questions]

A community project with a large number of stakeholders is scheduled for delivery in six months. The project manager asked the business analyst to ensure an effective requirements elicitation.

What should the business analyst do?

  • A. Engage a consult ant that is familiar with the community needs.
  • B. Organize a workshop with the sponsor and major stakeholders.
  • C. Ask the project coordinator to facilitate some of the workshops.
  • D. Invite both internal and external stakeholders to the workshops.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month, 1 week ago
Selected Answer: D
Why the other options are less appropriate: A. ❌ While a consultant might add value, this doesn't replace direct stakeholder involvement. B. ❌ This limits input to only a subset of stakeholders and may miss critical community perspectives. C. ❌ The focus is on who facilitates, not on who participates—which is key for elicitation.
upvoted 1 times
...
8a6d137
3 months, 4 weeks ago
Selected Answer: B
Organizing a workshop with the sponsor and major stakeholders is a fundamental step in effective requirements elicitation. This workshop allows for direct interaction with key project sponsors and stakeholders, ensuring their perspectives, needs, and requirements are understood thoroughly. Engaging with these essential parties at the outset of the project helps in gathering valuable insights, clarifying expectations, and aligning the project goals with the community needs. While inviting both internal and external stakeholders to the workshops is generally a good practice, focusing on the sponsor and major stakeholders first allows for concentrated attention on the most critical requirements. As the project progresses, the business analyst can continue to engage with a wider range of stakeholders as needed to ensure a comprehensive understanding of community needs.
upvoted 1 times
...
Andrew_1980
1 year ago
Selected Answer: D
A workshop is needed here. There should be representatives of all stakeholder groups.
upvoted 1 times
...
ebbff63
1 year, 2 months ago
Selected Answer: D
A - No - Consultant cannot capture the full diversity of stakeholder views as effectively as direct engagement through workshops. B - No. might exclude other crucial voices C- No. doesn’t ensure effective requirements elicitation D - Yes . By including both internal (project team members, organizational staff) as well as external stakeholders (community members, local authorities,etc), the business analyst can collect a broad range of inputs and needs, which is necessary for the success of community-oriented projects.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...