exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 340 discussion

Actual exam question from PMI's CAPM
Question #: 340
Topic #: 1
[All CAPM Questions]

A project manager has the task of determining the deliverables for a six-month project using a predictive approach. How should the project manager determine which processes to include in the project management plan?

  • A. Identify the processes and deliverables for only the current phase first.
  • B. Discuss the processes and deliverables needed to meet the project objectives with the team.
  • C. Integrate hybrid approach processes and deliverables to meet the short delivery time line.
  • D. Follow organizational methodology and produce all required deliverables.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Haq47
5 months, 2 weeks ago
Selected Answer: D
D. Follow organizational methodology and produce all required deliverables. Explanation: According to PMI, when using a predictive (waterfall) approach, the project manager typically adheres to the organization's established methodology, which outlines the processes and deliverables needed for project success. The project management plan is comprehensive and developed upfront, covering all phases and deliverables of the project to meet the defined objectives.
upvoted 1 times
8a6d137
1 week, 2 days ago
Thats wrong. It negates principial of Tailoring.
upvoted 1 times
...
...
Vangelis_1980
9 months ago
Selected Answer: B
The project manager should B. Discuss the processes and deliverables needed to meet the project objectives with the team. In a predictive (or traditional) project management approach, it’s essential to involve the project team in the planning process. By discussing the processes and deliverables with the team, the project manager can gain valuable insights, align everyone’s understanding, and ensure that the project objectives are met effectively. This collaborative approach helps create a comprehensive project management plan that considers all relevant aspects and sets the project up for success.
upvoted 4 times
...
ebbff63
11 months, 1 week ago
Selected Answer: B
Ans:B Discuss the processes and deliverables needed to meet the project objectives with the team.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago