A project team member is reviewing the scope of a task with an end user and realizes that requirements have changed. Which project artifact should be used in this situation?
Nope not scope management plan.
requirements changes are first updated in requirements management plan that is in Proj Mgmt Plan. As a result of that then Scope management plan will be updated. Remember the Project Manager mindset....they are asking what to do first
The scope management plan outlines how the project team will define, validate, and control the project scope. When a team member discovers a change in requirements during a task, it directly impacts the project scope. Therefore, the scope management plan should be consulted to determine the process for managing scope changes. This plan typically includes procedures for change requests, impact assessments, and approval processes.
Ans A - scope management
Its a part of project management plan that tells how the scope will be defined, developed, and controlled, even when a change is needed when requirements change.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
8a6d137
1 week, 1 day agoVangelis_1980
9 months, 1 week agoebbff63
11 months, 1 week ago