Actual exam question from PMI's PgMP
Question #: 8
Topic #: 1
[All PgMP Questions]

Andy is the program manager of the HQN Program. This program is nearing its completion and there is still $25,000 left in the program budget. Andy has asked the program team to identify some extra deliverables that can be included in the program scope to improve the program deliverable but also to use all of the funds in the budget. What term is assigned to the actions that Andy is trying to do in this instance?

  • A. Value-added change requests
  • B. Zero based budgeting
  • C. Integrated change control
  • D. Gold plating
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
tungdt
11 months ago
D is right answer
upvoted 1 times
...
omankoman
12 months ago
Selected Answer: D
D is right answer.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...