exam questions

Exam PMI-SP All Questions

View all questions & answers for the PMI-SP exam

Exam PMI-SP topic 1 question 1 discussion

Actual exam question from PMI's PMI-SP
Question #: 1
Topic #: 1
[All PMI-SP Questions]

Once the project's WBS has been created what process may happen next?

  • A. Estimate activity resources
  • B. Define activities
  • C. Estimate activity durations
  • D. Sequence activities
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
The define activities process is the process that may begin once the project's WBS has been completed and approved. It is possible, in some projects, to complete the WBS and the activity list at the same time.
Incorrect Answers:
A: Estimating activity resources is dependent on the activity list, so this choice is not valid.
C: Estimate activity durations are dependent on the activity list, so this choice is not valid.
D: Sequencing the activities cannot happen until the activity list has been created.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Aditech
3 months, 3 weeks ago
Selected Answer: B
Example: WBS Work Package: (Build Foundation) In the Define Activities process, it is broken into specific tasks like: Excavate site Lay reinforcement bars Pour concrete Cure concrete Example: WBS Work Package: "Build Foundation" In the Define Activities process, it is broken into specific tasks like: Excavate site Lay reinforcement bars Pour concrete Cure concrete WBS Work Package: (Build Foundation) In the Define Activities process, it is broken into specific tasks like: Excavate site Lay reinforcement bars Pour concrete Cure concrete
upvoted 1 times
...
Aditech
3 months, 3 weeks ago
Selected Answer: B
The correct answer is: B. Define activities Explanation: Once the Work Breakdown Structure (WBS) has been created, the next process is to Define Activities. This involves breaking down the work packages from the WBS into individual activities that are necessary to complete the project. These activities form the foundation for the remaining planning processes, such as estimating resources, durations, and sequencing.
upvoted 1 times
...
omankoman
5 months, 2 weeks ago
Selected Answer: B
B is right answer.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago