Given the following information, what is the schedule variance (SV) for this project?


Early start date (ES): 16 weeks -

Actual time: 12 weeks -
Schedule performance index (SPI): 1.3

  • A. 5
  • B. 2
  • C. 3
  • D. 4
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
flee
11 months, 1 week ago
Selected Answer: C
ES = 16 AT=EV=12 SPI = EV/PV SV = EV-PV 1.3 = 12/PV PV = 9.23 (To confirm : SPI=EV/PV = 12/9.23 = 1.3 = same with the information given.) Thus SV = 12 - 9.23 SV = 2.769 SV ~ 3
upvoted 4 times
...
1wheel
11 months, 3 weeks ago
SPI = EV/PV so EV =12 weeks. Based off our option PV being 2 would be 12/10 = 1.2 12/9 = 1.33333 so if PV is 15 weeks SV = EV-PV of 15-12 =3. Based off that i'd say answer is C for 3.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...