A backwards path calculation estimates that the last work package will be completed 24 days from this coming Monday. The scrum team operates in two-week sprints.
Correct but keep in mind that two-week sprints are 10 working days. Number of sprints = Total days / Days per sprint --> 24/10 = 2.4. So the closest round number is 2.