A project manager joins an existing project. One project stakeholder is unhappy with the frequency and types of project updates received and has made a request for more information to be shared.
What should the project manager do next?
A.
Consult the scope baseline document to track project updates.
B.
Update the project communications management plan immediately.
C.
Inform the stakeholder to wait for the annual stakeholder review meeting.
D.
Schedule a meeting with the stakeholder to better understand their request.
D. Schedule a meeting with the stakeholder to better understand their request.
By scheduling a meeting with the stakeholder, the project manager can gather valuable insights and ensure that future communications align with the stakeholder's expectations, thereby enhancing stakeholder satisfaction and project collaboration.
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
MonBouj
7 months, 1 week agovictory108
7 months, 2 weeks agoomankoman
11 months, 1 week agoDammielolz
11 months, 2 weeks agomartinx84
11 months, 2 weeks ago