exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1389 discussion

Actual exam question from PMI's PMP
Question #: 1389
Topic #: 1
[All PMP Questions]

During a team meeting the new agile project manager becomes aware that there are many complaints from the customer regarding project stability and other critical issues. A team member states that the deliverables were developed by experienced employees who confirmed that the project was stable.

How should the new project manager address these concerns?

  • A. Allow the agile team to decide what they are able to deliver in each iteration
  • B. Ask the team for additional feedback and add tasks to the task board
  • C. Document the customer's complaints and critical issues in the issue log
  • D. Hold a brainstorming session to identify the root cause of the complaints
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MonBouj
7 months ago
Selected Answer: D
D. Hold a brainstorming session to identify the root cause of the complaints It helps identify the root cause of the customer's complaints and enables the team to address the underlying issues. This proactive approach aligns with Agile principles of collaboration and continuous improvement.
upvoted 1 times
...
victory108
7 months, 2 weeks ago
Selected Answer: D
D. Hold a brainstorming session to identify the root cause of the complaints
upvoted 1 times
...
9RedFox_JB
10 months, 2 weeks ago
why? why not to document at first and then hold brainstorming session
upvoted 2 times
prokat_mashin_na_vicecity
7 months, 4 weeks ago
because its Agile project, where communications and meetings are over documentation
upvoted 1 times
...
...
omankoman
11 months, 1 week ago
Selected Answer: D
D is the answer.
upvoted 1 times
...
martinx84
11 months, 1 week ago
Selected Answer: D
Hold brainstorming session to find root cause
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...