exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1281 discussion

Actual exam question from PMI's PMP
Question #: 1281
Topic #: 1
[All PMP Questions]

A project manager is reviewing the lessons learned for an historical project. The review identifies that the client's engineer was adamant that they review all changes, even those not identified in the contract.

How should the project manager deal with this when planning the project?

  • A. Update the project charter with this information regarding change management.
  • B. Talk with the client to ensure they are aware of the change management procedure.
  • C. Ensure the change management plan highlights this requirement to prevent future issues.
  • D. Update the project risk register to identify this risk and describe how to mitigate the issue.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
sblivia
1 month ago
Selected Answer: C
By incorporating this requirement into the change management plan, the project manager can ensure that all stakeholders, including the client's engineer, are aware of the procedure for reviewing changes. This proactive step helps to prevent misunderstandings and ensures that the project team and the client are aligned on how changes will be managed throughout the project.
upvoted 1 times
...
victory108
7 months ago
Selected Answer: B
B. Talk with the client to ensure they are aware of the change management procedure
upvoted 1 times
victory108
5 months ago
Answer is C. Ensure the change management plan highlights this requirement to prevent future issues
upvoted 1 times
...
...
Anitak
10 months, 3 weeks ago
The answer should be D not C.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago