exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 364 discussion

Actual exam question from PMI's CAPM
Question #: 364
Topic #: 1
[All CAPM Questions]

An adaptive team is in the process of merging a legacy system from an acquired company. In order to check the project status and manage the flow of work, they are using a scrum board for this project.

What data should be included in this information radiator?

  • A. Key performance indicators (KPIs) and baseline
  • B. Product and sprint backlog
  • C. Burndown and burnup charts
  • D. Increments and bottlenecks
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
8a6d137
3 weeks, 6 days ago
Selected Answer: B
Explanation In an adaptive team using Scrum methodology, the scrum board serves as an essential information radiator for tracking project progress and managing workflow. For a project involving the merger of a legacy system from an acquired company, the scrum board should primarily include the product backlog and sprint backlog. Product Backlog: This is a prioritized list of all features, requirements, enhancements, and fixes that constitute the changes to be made to the product. In this case, it would include all the tasks necessary to merge the legacy system successfully. Sprint Backlog: This is a subset of the product backlog, containing the items selected for the current sprint, along with the plan for delivering them. It represents the team’s immediate focus and commitment for the ongoing sprint.
upvoted 1 times
...
Fav24
7 months, 1 week ago
The Scrum board is a visual tool in Agile that tracks work progress. It shows tasks from the product backlog (all project tasks) and the sprint backlog (tasks for the current sprint), helping the team see what’s in progress and what’s done.
upvoted 3 times
...
flee
10 months, 2 weeks ago
Selected Answer: C
Burndown and burnup charts are essential tools in Scrum for tracking progress. They provide visibility into the remaining work (burndown chart) or the completed work (burnup chart) over time. These charts help the team and stakeholders understand if the project is on track to meet its goals and deadlines. Key performance indicators (KPIs) and baseline measurements (option A) are used for monitoring overall project health and performance but are usually tracked separately. Product and sprint backlogs (option B) are managed and updated within the team but are not typically displayed on the scrum board itself. Increments and bottlenecks (option D) are important to identify and address during project execution but are not commonly shown on the scrum board.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago