A project manager is in the process of onboarding resources to start work on a project. Which of the following components of a project management plan will the project manager update after completing this activity?
A.
Resource management plan and cost baseline
B.
Resource management plan and lessons learned register
C.
Resource management plan and procurement management plan
Resource management plan: This document outlines how resources (both human and physical) will be identified, acquired, utilized, and managed throughout the project. After onboarding resources, updates to this plan may include new roles filled, changes in resource availability or capacity, and any adjustments to resource allocation strategies.
Cost baseline: The cost baseline is a part of the overall project baseline and represents the authorized budget for the project work. Onboarding resources can impact project costs, such as salaries, contractor fees, or other resource-related expenses. Therefore, updates to the cost baseline may be necessary to reflect these changes.
Preassignment refers to assigning specific resources to project roles BEFORE the project officially begins. Onboarding resources happens after the decision is made to bring them onto the project. This could be considered if it’s “Reassignment”.
upvoted 4 times
...
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
flee
11 months, 1 week ago