Where are negative risks recorded?

  • A. Negative risk register
  • B. Risk management plan
  • C. Risk register
  • D. Issues log
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Nugi
4 months, 2 weeks ago
Selected Answer: C
There is only Risk Register for both positive/negative risks.
upvoted 1 times
...
tungdt
10 months, 3 weeks ago
C is right answer
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago