exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1351 discussion

Actual exam question from PMI's PMP
Question #: 1351
Topic #: 1
[All PMP Questions]

A bridge construction project has been paused due to a political change in the local government. After almost 5 years, the new government would like to resume the project, and a project manager is assigned.

What should the project manager do first?

  • A. Prepare an estimate of the time and cost to complete this project.
  • B. Study the project's lessons learned to understand why it was paused.
  • C. Meet the new stakeholders and understand their expectations.
  • D. Examine the project's business case in order to resume the project.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Schwery
4 months, 1 week ago
Selected Answer: D
The correct answer is: D. Examine the project’s business case in order to resume the project. Explanation: The business case is a critical document that outlines the justification for the project’s existence, including its value, objectives, and alignment with organizational goals. After a long pause, circumstances, priorities, or the economic environment might have changed. Examining the business case ensures that resuming the project is still viable and aligned with the new government’s strategic objectives before committing resources. Why not C: Stakeholder engagement is crucial but should occur after confirming the project’s business case to avoid unnecessary stakeholder discussions for a project that may no longer be viable.
upvoted 1 times
...
victory108
7 months, 1 week ago
Selected Answer: D
D. Examine the project's business case in order to resume the project
upvoted 2 times
...
c8ee0e6
10 months, 2 weeks ago
The question says first thing and as per the choices, the PM will need to understand the new stakeholder's expectations.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago