A program manager is identifying and verifying risks as outlined in the risk management plan.
The results will be recorded in which of the following?

  • A. Risk register
  • B. Risk monitoring and control
  • C. Risk response planning
  • D. Risk mitigation strategy
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
tungdt
10 months, 2 weeks ago
A is correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...