The sponsor approaches the project manager with new features they want added to the project. The project is 95% complete, but the sponsor insists that continued support for the project relies on the addition of the new features.

What should the project manager do?

  • A. Implement the new features after assessing the impact.
  • B. Reject the new features since it amounts to gold plating.
  • C. Assess the impact of the features and refer it to the change control board (CCB).
  • D. Add the new features to avoid losing the sponsor's support for the project.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
sblivia
1 month ago
Selected Answer: C
Assess the impact
upvoted 1 times
...
victory108
7 months, 1 week ago
Selected Answer: C
C. Assess the impact of the features and refer it to the change control board (CCB)
upvoted 1 times
...
martinx84
10 months ago
Selected Answer: C
Assess the impact
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago