Which project life cycle follows a plan reviewed and approved by the stakeholders?

  • A. Adaptive
  • B. Iterative
  • C. Incremental
  • D. Predictive
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Vangelis_1980
9 months, 1 week ago
Selected Answer: D
D. Predictive Explanation: Predictive project life cycle is characterized by a detailed plan created upfront, reviewed, and approved by stakeholders before the project begins. This approach is often used for projects with well-defined requirements and low levels of uncertainty.   Let's briefly look at the other options: Adaptive: This life cycle is flexible and adjusts to changes throughout the project.   Iterative: This life cycle involves repeated cycles of design, development, and testing.   Incremental: This life cycle delivers the project in smaller increments or portions.   None of these options emphasize a detailed, pre-approved plan like the predictive life cycle does.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago