C. Schedule the tasks in parallel
Explanation:
To ensure on-time delivery for a small project with time constraints, scheduling tasks in parallel is the most effective approach. This means performing multiple tasks simultaneously, whenever possible, to reduce overall project duration.
Increasing quality review cycles might improve quality but would likely extend the project timeline.
Scheduling tasks in sequence means doing one task at a time, which is generally less efficient for time-constrained projects.
Expanding the project scope would almost certainly increase the project duration, contradicting the goal of on-time delivery.
By maximizing parallel work, the project manager can optimize the use of available resources and accelerate project completion.
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Vangelis_1980
9 months, 1 week ago