A project manager is assigned to a project related to taxes, which will be managed using an agile approach. By reviewing lessons learned from a previous project, the project manager discovers that a key stakeholder is an expert on taxes and is willing to help.
How should the project manager leverage this information?
MonBouj
8 months, 1 week agovictory108
8 months, 1 week agod370e49
9 months, 1 week agoKim222
10 months, 2 weeks agomatt_joy
10 months, 2 weeks ago