A project manager is working on a complex project and is unsure about planning, executing, monitoring and controlling the project. Match the phrase on the left with the correct statement on the right.
Risks and costs --> are controlled as requirements and constraints emerge.
Requirements --> are elaborated frequently during delivery.
Changes --> are incorporated in real-time during delivery.
Key stakeholders --> are continuously engaged throughout delivery.