Exam PMP topic 1 question 1405 discussion

Actual exam question from PMI's PMP
Question #: 1405
Topic #: 1
[All PMP Questions]

A project manager is in the middle of an agile project comprised of 100 user stories broken down into five iterations. Each user story is worth US$50. The actual expenditure is US$2,000 and 50 user stories have been delivered.

Which statement is true?

  • A. The project is under budget and on schedule.
  • B. The project is over budget and behind schedule.
  • C. The project is under budget and behind schedule.
  • D. The project is on budget and on schedule.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Dekoreh
4 months, 1 week ago
Selected Answer: A
EV (amount of money worth work done) = Actual % complete x BAC (Budget on the project); PV = Planned Complete % x BAC ; CV = EV – AC (amount of money already spent); CV = EV – AC CPI = EV/AC , SV = EV – PV, SPI = EV/PV PV= 50 x 50 $ = 2500$, AC = 2000$, EV = 50/100 x BAC = ½ 5000$, = 2500$, CV = EV -AC = 2500 – 2000 = 500$ CPI = 2500/2000 = 1.25, (project is under budget), SV = 2500 – 2500 = 0, SPI = 2500/2500 = 1 (project is on schedule)
upvoted 1 times
...
Doladeji
5 months ago
Selected Answer: A
The Actual cost of Work (ACW) is $2500 - i.e $2000 + 50 stories x $50 = $2500 Budgeted Cost of Work (BCW) is 2000 - i.e given in the question The ACW is less than the BCW - i.e ACW < BCW = Project is under Budget NOTE: The questions says the project is midway and 50 stories have been delivered at midway, meaning the project is on SCHEDULE if it has achieved 50% (50 stories) at Midway. So, Project is UNDER BUDGET and ON SCHEDULE
upvoted 1 times
...
MonBouj
7 months ago
Selected Answer: A
Budget Status: Budgeted Cost of Work (BCW): US$2,500 (for the 50 completed stories) Actual Cost (AC): US$2,000 Since AC < BCW, the project is under budget. Schedule Status: Planned Value (PV): The value of work planned to be completed by now. For 50 completed stories, PV = US$2,500. Since 50 stories were planned to be completed and have been completed, the project is on schedule. => A. The project is under budget and on schedule.
upvoted 2 times
...
victory108
7 months ago
Selected Answer: A
A. The project is under budget and on schedule
upvoted 2 times
...
VladRadulescu
7 months ago
Selected Answer: A
A. The project is under budget and on schedule.
upvoted 2 times
...
Ngho
7 months, 1 week ago
A. The project is under budget and on schedule. Here’s why: 50 user stories have been delivered, and each story is worth $50, meaning the earned value (EV) is 50 x $50 = $2,500. The actual expenditure is $2,000, which means the actual cost (AC) is $2,000. Since the EV ($2,500) is greater than the AC ($2,000), the project is under budget. The fact that 50 user stories have been delivered (out of 100, halfway through the project) suggests the project is on schedule if it’s supposed to deliver all 100 stories across 5 iterations. Thus, the project is both under budget and on schedule.
upvoted 2 times
...
prokat_mashin_na_vicecity
7 months, 2 weeks ago
The question CLEARLY states that "an agile project comprised of 100 user stories". No matter how many iterations, number of US is fixed. So, EV=2500. Project is under budget and on schedule.
upvoted 1 times
...
funmis4
8 months, 1 week ago
5 iterations- that means an assumption of 100/5 =20 per each iteration . The budget then is $50 x 100 = $5,000 So if the question says at the middle of the project only $2000 has been expended , then it is under the budget @ $50 per user story
upvoted 2 times
...
Kim222
8 months, 3 weeks ago
Selected Answer: C
This is C
upvoted 1 times
d370e49
8 months ago
Explain your reasoning.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago