exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1341 discussion

Actual exam question from PMI's PMP
Question #: 1341
Topic #: 1
[All PMP Questions]

A project manager identifies a risk that has a high probability of occurring. How should the project manager manage this risk?

  • A. Assign a qualified team member to be the risk manager for the project.
  • B. Remove the user stories associated to that risk and avoid the impact to the project deliverables.
  • C. Submit a change request to transfer the risk to a third party in case it becomes an issue.
  • D. Ask the team to monitor the risk and provide an alert if it becomes an issue.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Schwery
5 months ago
Selected Answer: A
The best approach to manage a risk with a high probability of occurring is: A. Assign a qualified team member to be the risk manager for the project. Explanation: For a risk with a high probability of occurrence, the project manager must actively manage it by assigning responsibility to someone who can monitor and mitigate the risk. This person, often called a risk owner, ensures that specific actions are taken to address the risk. They also continuously monitor the risk and adjust strategies as needed to minimize its impact.
upvoted 1 times
...
Okstm
5 months, 3 weeks ago
Selected Answer: C
C. Submit a change request to transfer the risk to a third party in case it becomes an issue. transferring the risk to a third party, such as an insurance provider or a contractor, can reduce the impact on the project. This approach can be especially relevant for risks that are likely to happen and could severely affect the project. D. Ask the team to monitor the risk and provide an alert if it becomes an issue- Monitoring is important, but with a high-probability risk, it’s better to take proactive steps to manage it rather than just wait for it to occur.
upvoted 1 times
...
victory108
7 months, 1 week ago
Selected Answer: A
A. Assign a qualified team member to be the risk manager for the project
upvoted 1 times
victory108
5 months ago
Assigning is not enough so this is C. Submit a change request to transfer the risk to a third party in case it becomes an issue
upvoted 1 times
...
...
funmis4
8 months, 2 weeks ago
The entire should look out for risks
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago